Payment method: "4-step" installmentsPayable upon reservation and contract signing.
- 2nd payment: 20% (February 2026)
Payment upon completion of the first phase of construction.
- 3rd payment: 20% (August 2026)
Payment upon completion of frame construction.
- 4th payment: 20% (February 2027)
Payment upon completion of finishing work.
- 5th payment: 20% (August 2027)
Final payment upon handover of the property.
Payment method: Quarterly installmentsPayable upon reservation and contract signing.
- 2nd payment — 10% (February 2026)
Stage: Start of construction.
- 3rd payment — 10% (May 2026)
Stage: Foundation completion.
- 4th payment — 10% (August 2026)
Stage: Frame completion.
- 5th payment — 10% (November 2026)
Stage: Exterior finishing.
- 6th payment — 10% (February 2027)
Stage: Interior finishing.
- 7th payment — 10% (May 2027)
Stage: Installation of utility systems.
- 8th payment — 10% (August 2027)
Final stage before handover.
10% discount for 100% payment